Project
Reporting: examples
This example is a task leader’s report for an important component
on an aircraft. Note that after the header information, there are three
report sections.
The first section shows a Gantt chart of summary
level tasks. It has a vertical line indicating the report date
and shaded bars
showing qualitative
progress.
The second chart is an earned value chart
showing PV and EV. Notice that there is a small gap between
the two indicating
that the task
is a little
behind schedule.
The third section is a table showing all the
quantitative data. It has data fields that are refreshed at
any time from
a master MIS data base.
The task leader uses these data to change the two charts each month,
and the report takes only about five minutes to prepare. |