Cost/Schedule
Control – Basic concepts and terminology
When we created the Project Baseline, we learned how it is developed
from the Gantt schedule and the resources assigned to the timelines.
Therefore, the baseline combines elements of cost and schedule. The baseline
budget establishes the basis for integrated cost/schedule control.
|