An
Example of Integrated Cost/Schedule Control – three scales
of measure
We can express this baseline for the drawings task in money,
hours, or number of work products. If we list all our estimates
and assumptions on the project, we can complete the objectives.
The drawings are estimated to take 10 hours per drawing, and
the charge rate for draftsmen is 10 Euros per hour (our draftsmen
are notoriously underpaid).
|
Week #1 Status |
No. Dwgs. |
Hours |
€ (or
%) |
- PV
(Baseline)
|
14
|
140
|
€ 1,400
|
...and we can construct a graph to represent this... |