An Example of Integrated Cost/Schedule Control – unequal baseline

Now we are going to distribute the baseline for task C: create 20 drawing in 2 weeks.

Please note that this time we have not distributed the work evenly over the two weeks. Instead, we have scheduled 14 drawings the first week of the task and 6 drawings the second week of the task.