Earned
value measures work accomplishment, not actual costs
The planned value baseline can
be used to control both cost variances and schedule variances.
We will discuss variances
more in the lesson on Project Control. During execution of
the project, the team measures the amount of work done in each
time period. The “work done” has a value – it
is the same value created during planning (either cost, hours,
or number of work products delivered). Remember, earned value
is the budget assigned to the amount of work done, not the “out-of-pocket” actual
cost to pay for that work.
|