Using
the baseline and earned value to measure schedule variance
This graph demonstrates two different
ways of measuring schedule variance using the cost baseline
and earned value. On the horizontal
axis, we can see the time variance between the date we planned
to accomplish a certain amount of work and the date we actually
accomplished that amount of work. On the vertical axis we can
measure the difference between the budgeted value (earned value)
of the “work done” to a specified date and the
budgeted value of the “work planned” at the same
date. This is called the schedule variance (SV).
|