Building
the Baseline: Step 4 (optional) – Remove the Gantt chart
bars and leave the cumulative baseline
You
may want to remove the underlying Gantt chart bars to
simplify the presentation of the cost baseline. But always
remember that the cost baseline is derived from estimating
costs for work packages that are spread over time.