The
Cost Baseline is the Basis for Cost and Schedule Control
Whether you are talking about economic
processes, physiological processes, electrical processes, mechanical
processes, or project
processes, a baseline is essential for control. The basic model
for control, shown below, requires a baseline so you can perform
the first step of measurement – measuring the difference
between planned work and work actually done during execution.
|