Determining
the critical path – step 3: The critical path
Now we are ready to determine the critical path. The difference between
the early date and the late date for each node is the slack associated
with the task before the node. Those nodes for which the early and late
date are the same have no slack, and the tasks linking them are on the
critical path.
|