Determining
the critical path: In summary
- Add all activity duration estimates
from left to right (earliest completion time) and record
above the nodes.
- Subtract all activity duration estimates from
right to left (latest completion time) and record below
the nodes.
- The critical path is that chain of events
where there is no slack – the
earliest and latest times are the same

|