Determining
the critical path – step 1: The forward pass
The first step is to calculate the earliest date you can reach each node,
starting at the beginning of the project (node 1) and adding the duration
of the successor activities to determine the earliest date for each subsequent
node. Mark the days to reach the node on top of each node.
Click the image above to hear an explanation.
|