And
a VERY IMPORTANT note on PROCESS
The WBS must belong to the project team. This means it should
be created by the team, not by an individual and handed to
the team. The WBS should be developed in a team setting, with
the core team from the various functions represented. A Small
Group Dynamic (SGD) occurs in team sizes from four
to six persons,
such that team members form close alliances and hold themselves
accountable for results. Cross-functional teams of this size
develop the full WBS through a series of meetings, with the
higher level team members developing the higher levels of the
WBS and the lower level team members working in separate groups
to develop the lower levels.
We strongly recommend that the
WBS be developed in a team setting first, and input
the information into your computer program
only after the team has build it “hands-on.” |