… and a real, live example
This chart depicts the cost and schedule consequences of the “change order game” caused by vague and ambiguous objectives on a subcontracted project for an international oil company: nearly 100% cost overrun, a 50% schedule delay, and no end in sight. The company cancelled the contract and put procedures in place to get agreement on the detailed project objectives in writing by all stakeholders during planning.