rolling wave planning: a method of “progressive elaboration” planning that holds the definition of mid-term and long-term tasks at a higher WBS level than near-term tasks. Often used when the project involves a process of discovery such that later tasks can not be fully specified until current tasks are completed. The detailed planning horizon is generally three to six months.