Answer
to Question 10
The importance of asking team members to report on percent
complete is that:
a) it provides information to top management necessary
for them to manage by objectives (MBO),
b) provides data
from each WBS element showing that the project manager
is under
control,
c) it causes the team member to measure accomplishments
to date enabling decentralized control,
d) it is plotted
on the Gantt chart as shaded area on each bar.
|