Question
11
What is risk contingency?
a) money to cover extra costs which are likely to happen
on the project,
b) money to cover uncertainties in cost
estimates within the defined scope and
schedule,
c) money to cover changes in scope,
d) the project manager's
fund to cover miscellaneous costs.
|