Question 10

The importance of asking team members to report on percent complete is that:

a) it provides information to top management necessary for them to manage by objectives (MBO),

b) provides data from each WBS element showing that the project manager is under control,

c) it causes the team member to measure accomplishments to date enabling decentralized control,

d) it is plotted on the Gantt chart as shaded area on each bar.