Organizational
Requirements – monitor trends
As we said earlier, it’s
not enough to look at snapshots in time when trying to control
a project. A trend chart gives
additional information. In this example, the team is getting
behind schedule. What is a primary reason for this? Not enough
resources? Sure enough, cost expenses are under plan. But notice
what happens near the end of September: the team is getting
further behind schedule and cost is overrun. This situation
needs immediate attention.
|