Example of Integrated Cost/Schedule Control – status
the task
Now we status the drawing task
after one week of work, and discover that we have only completed
12 drawings but we have
expended 180 hours of labor at a cost of € 1800.
Click on underlined letters to hear an explanation.
|
Week
#1 Status
|
No.
Dwgs.
|
Hours
|
€ (or
%)
|
- PV
(Baseline)
- AC
- EV
|
14
12
|
140
180
|
€
1,400
€ 1,800
|
Click on underlined letters to hear an explanation.
|