An Example of Integrated Cost/Schedule Control – status the task
Now we status the drawing task after one week of work, and discover that we have only completed 12 drawings but we have expended 180 hours of labor at a cost of € 1800.

Click on underlined letters to hear an explanation.

 
Week #1 Status
No. Dwgs.
Hours
€ (or %)

  1.       PV
    (Baseline)

  2.      AC

  3.      EV

14




12

140


180

€ 1,400


€ 1,800