| What
                  will it cost to accelerate the schedule?We’ve all heard of “throwing money at a
                  project” to try to shorten the timeline. But where should
                  you throw the money? If you are going to spend more money in
                  order to shorten task durations, it only makes sense to stick
                  to the critical path – shortening tasks not on the critical
                  path won’t shorten the overall project. However, as you
                  shorten tasks, be aware that a new critical path may emerge.
 Another
                    common practice is to calculate the cost per unit time to
                  shorten each task. Then, throw your money first at the tasks
                    that are the least expensive to shorten per unit of time.  This is a PDM (activity-on-node)
                  diagram of a project with six tasks. The duration of each task
                  is written above each node.
 Can you spot the critical
                  path? |