Infeasible 8-Day Schedule (continued)
The result is a resource
feasible schedule, 10 days long rather than 8 days long.
Leveling
resources within time constraints occurs often in
project management, and it can become an activity trap. You
can’t force 3 cups of milk into a 2 cup jar. Something’s
got to give: time, resource or scope. In this example, the
resource constraint controls, and time must be extended to
maintain the same scope.
|