Resource
                  Infeasible 8-Day Schedule (continued) 
                  How are we going to deal
                  with this? There are several possibilities: 
                
                  - 
                    
 Ask
                          the task leader of “C’ if the work could be
                          done with 2 people in 3 days. If he or she says “yes”,
                          the problem is solved.
                          
                      
                   
                  - 
                    
Move “C” downstream
                          within available slack. This does not work, as it just
                      moves the
                          need for 5 people downstream. 
                           
                     
                   
                  - 
                    
A
                          resource feasible solution is to move “C” into
                              the A-D-F critical path. The only logic constraint on “C” is
                        that it must follow “A,” as does “D.” 
                   
                    |