Examples
of Different WBS: (continued)
… A cruise
ship modification project, two different WBS to level 1
The project team created
two fundamentally different work breakdown structures for the
same project: chronological and functional. These are both
shown on the next page. They evaluated advantages and disadvantages
of each structure for application to their type of business.
The top WBS emphasizes a chronological flow of work through
the project life cycle. The bottom one emphasizes work done
within functional departments. Please listen to some of the
conclusions below.
|
Under
what conditions might the top WBS give you better management
control. Under what conditions might the bottom WBS give
you better management control. Click on the highlighted
words to hear some ideas.
|
For this project, the
project team concluded that the chronological WBS was a better
approach. The critical path was easier to determine, there
was more sense of urgency between team members to assure the
work flowed quickly, and communications between the team was
actually enhanced.
|