Z&A Power Systems
(Engineering, Procurement & Construction)
Projects to Date
• Developing Electric Power Transmission and Distribution Lines and Substations since 1997
• South Dagon Utility (SDU): Power Trading and Power Distribution Utility under Yangon Electricity Supply Board (YESB)
• First Private Power Distribution Utility in Yangon
• South Dagon Township and Industrial Zone
• Serving over 60.000 Consumers
• Grid Modernization
• Maintenance Procedures Improvement
Projects in Progress
• Entered Power Sector IPP in 2012
• Project Hlawga: 50MW Power Plant.
• MOA (50MW) signed by May 2013
• Phase 1 (25MW) – COD May 2013 on PPA with MEPE
• Phase 2 (25MW) – PPA signing with MEPE March 2014 & COD operated from April 2015
• Phase 3: + 25MW (MOU under discussion)
• Waste to Energy Project in Yangon for 600 Tons/Day to generate 15.4 MW
PROJECT EXPERIENCES OF POWER SYSTEMS
OUR EXPERIENCES
Project Title: The Supply of 132 kV Substation - 2 Lots, 66 kV Substations – 4 Lots, 66 kV Substation Extensions – 4 Lots,
66 kV Transmission Lines – 2 Lots, 33 kV Substation – 1 Lot
Location: (1) Shwetaung (2) Mone H.P.P (3) Tat Kone (4) Tanuaung (5) Taungdwingyi
Owner: Myanma Electric Power Enterprise and Directorate of Defense Industries
Start Date: 15 August 2006
Project Amount: 16,300,000.00 USD
Date of Completion: August 2008
OUR EXPERIENCES
Contract No: F 58 (AS) 2008-2009
Project Title: The Supply 132/66/11 kV, 60MVA Substation Materials
Project Buddhakone
Location: Buddhakone
Owner: Water Resources Utilization Department
Start Date: 23 March 2009
Project Amount: 2,950,000.00 USD
Completed Date: August 2010
OUR EXPERIENCES
Contract between International Contact and Zeya & Associates for 230/33/11 kV, 100 MVA Substation Materials
Project Title: The Supply 230/33/11 kV, 100MVA Wartayar Substation Materials
Location: Wartayar Industrial Zone
Owner: DHSHD, Ministry of Construction
Start Date: June 15, 2011
Project Amount: CIF 3,705,600.00 USD
Date of Completion: October 2012
OUR EXPERIENCES
Contract No: 105/EL-MEPE(PTP)/2010-2011|
Project Title: Supply 230/66/11 kV, 100 MVA Ahlone Substation Materials
Location: Yangon
Owner: Myanma Electric Power Enterprise
Start Date: May 24, 2010
Project Amount: 1,800,000.00 Euro CIF
Date of Completion: February 2013
Experiences of Power Generation Plant
Sr No |
Project Name | Capacity | Completion | Scope |
1 | Hlawga Gas Engine Power Plant (Phase I) | 25 MW | May,2013 | EPC |
2 | Hlawga Gas Engine Power Plant (Phase II) | 25 MW | July, 2014 | EPC |
3 | Tharketa Diesel Engine Power Plant | 13 MW | Dec, 2014 | EPC |
4 | Myingyan Gas Engine Power Plant | 90 MW | Feb, 2019 | Plant Civil Work, Installation of 132kV Transmission Line and EPC of Gas Control/Metering Station |
5 | Magway Gas Engine Power Plant | 66 MW | Dec, 2019 | Plant Civil Work, EPC of 33kV Substation, Gas Pipeline (1.65 miles) and Installation of Gas Control/Metering Station |
6 | Kyun Chaung Gas Engine Power Plant | 20.54 MW | May, 2020 | Plant Civil Work, Installation of 66kV Substation and Gas Control/Metering Station |
7 | Tharketa Gas Engine Power Plant | 400 MW | June, 2020 | EPC of 10" Gas Pipeline (1.5 miles) |
8 | Kyauk Phyu Gas Engine Power Plant | 150 MW | June, 2020 | Installation of 230kV Transmission Line, EPC of 6" Gas Pipeline (866 Meter) and Gas Control/ Metering Station |
9 | Thanlyin Gas Engine Power Plant | 350 MW | June, 2020 | Installation of 230kV Transmission Line |
10 | Hlawga Gas Engine Power Plant (Extension) |
9.2 MW | Nov, 2021 | EPC |