|
|
Was: |
|
PV |
Planned Value |
BCWS |
How much work should be done? (Budget) |
AC |
Actual Cost |
ACWP |
How much did we spend to get the work done? |
EV |
Earned Value |
BCWP |
How much did we budget for the work
we did? |
BAC |
Budget at Completion |
|
How much did we budget for the whole project? |
EAC |
Estimate at Completion |
|
Given our progress, how much will the total
project cost? |
ETC |
Estimate to Complete |
|
How much more do we estimate the job will cost? |
VAC |
Variance at Completion |
|
How much over/under budget will we be? |
Cost Variance (CV) |
EV - AC |
Negative = Over budget, Positive = Under budget |
Schedule Variance (SV) |
EV - PV |
Negative = Behind schedule, Positive = Ahead of schedule |
CPI |
EV
AC |
I am getting ______ cents out of every dollar. |
SPI |
EV
PV |
I am progressing at ______ % of the volume of work I
wanted. |
EAC |
BAC
CPI |
At this time, we expect the total project to cost _____
dollars. |
ETC |
EAC-AC |
How much will it cost from now to finish? |
VAC |
BAC-EAC |
At the end, how much more/less will we spend? |