Cost/Schedule Control – SPI and CPI

There are two other control measures used as Key Performance Indicators (KPI): Schedule Performance Index (SPI) and Cost Performance Index (CPI).



Click here to view image at a larger size.

There are actually two versions of the SPI – the traditional version based on the work product count, cost, or labor hours (the traditional schedule variance), and an SPI (alternate) based on the time variance.