What will it cost to accelerate the schedule? (continued)
The chart shows the order in which you would throw money at the tasks to shorten the schedule if your only concern was cost effectiveness. In this example, the critical path does not shift as the tasks are shortened. If it did, you would have to calculate a new critical path each time you shortened a task.