What
will it cost to accelerate the schedule? (continued)
The chart shows the order in which you would throw money
at the tasks to shorten the schedule if your only concern was
cost effectiveness. In this example, the critical path does
not shift as the tasks are shortened. If it did, you would
have to calculate a new critical path each time you shortened
a task.

|