Scheduling
as part of the planning process
The schedule translates the previously made Work Breakdown
Structure into a set of timed assignments. The first step of
the scheduling process is to define the specific activities
that must be performed to accomplish the objectives for each
WBS element. Next, the team determines the dependencies between
activities (predecessors, successors, and how the activities
are linked together). If you can set the delivery date, then
estimate the amount of time for each activity given the available
resources. If you are given the delivery date, estimate the
resources and activity sequences needed to meet that date.
Once the schedule is agreed, it provides the
basis for direction setting, assessing project progress, taking
corrective action, and reporting project status. |