Question 16

When developing a planning budget, each team member:

a) establishes his/her target objective then adjusts a cost curve to meet that target.

b) creates a schedule of their respective tasks and distributes cost across the timelines.

c) add up cost categories into a single cost number.

d) uses a cost baseline from a previous projects with a similar scope of work.