Question
16
When developing a planning budget, each team member:
a) establishes his/her target objective then adjusts a
cost curve to meet that target.
b) creates a schedule of
their respective tasks and distributes cost across the
timelines.
c) add up cost categories into a single
cost number.
d) uses a cost baseline from a previous
projects with a similar scope of work.
|