Answer to Question 12 The project organization chart should have a "one-to-one" relationship with:
a) the project schedule. b) the functional department’s organization chart. c) the project work breakdown structure (WBS). d) the project procedures.
a) the project schedule.
b) the functional department’s organization chart.
c) the project work breakdown structure (WBS).
d) the project procedures.