Answer to Question 3

The key performance indicators for a project manager are:

a) actual dates vs. planned dates,

b) actual costs vs. planned costs,

c) actual plant reliability vs. planned plant reliability,

d) actual performance vs. planned performance on time, cost and scope in the approved project execution plan.