Risk
Analysis – Qualitative,
the probability/impact matrix
The P/I matrix is the simplest and most effective tool for
use by project teams to assess risk. They start by looking
at the WBS and assessing risk in tasks at the lowest level.
What is the probability that a risk will occur? If it does
occur, how bad will it be? “High-high” risks
should be re-planned to lower the likelihood that they will
occur, or lessen the severity. This is called Mitigation. “Medium-medium
risks should be addressed with a contingency plan, but not
necessarily be re-planned. “Low-low” risks can
be accepted – you can’t watch everything.
|