1
2
3
4
5
6
7
8
9
10

Project Experiences

GK Power Systems
(Engineering, Procurement & Construction)

 

Myanmar Central Power
(Power Generation)

 

Southern Dagon Utility
(Power Trading and Distribution)

 

Projects to Date

• Developing Electric Power Transmission and Distribution Lines and Substations since 1997
• Southern Dagon Utility (SDU): Power Trading and Power Distribution Utility under Yangon Electricity Supply Board (YESB)

     • First Private Power Distribution Utility in Yangon
     • South Dagon Township and Industrial Zone
     • Serving over 60.000 Consumers
     • Grid Modernization
     • Maintenance Procedures Improvement
go to SDU >>

 

Projects in Progress

• Entered Power Sector IPP in 2012
• Project Hlawga: 50MW Power Plantby MCP Co., Ltd.
     • MOA (50MW) signed by May 2013
     • Phase 1 (25MW) – COD May 2013 on PPA with MEPE
     • Phase 2 (25MW) – PPA signing with MEPE March 2014 & COD operated from April 2015
     • Phase 3: + 25MW (MOU under discussion)

go to MCP >>

 

Waste to Energy Project in Yangon for 600 Tons/Day to generate  15.4 MW

 

Way Forward

• Potential 120MW Power Plant at Various Locations in Myanmar (MOUs under discussion)
• Achieving 500MW power generation in aggregate capacity by 2017 (including Green Energy)

Green Energy >>

Myanmar Central Power Co., Ltd

MCP POWER PLANT – HLAWGA (50 MW) PROJECT

 

Type Of Plant               -   Open Cycle Reciprocating Gas Engines
Fuel                             -   Yadanar Natural Gas
Location                      -   Beside Existing Hlawga Gas Turbine Power Station
Installed Capacity        -   50 MW
Owner:                        -   Myanmar Central Power Company Limited
Date of MOU Signing   -  18 October 2012
Phase 1                       -   25 MW
Phase 1 COD               -   25.05.2013
Phase 2                       -    25 MW
Phase 2 COD               -    11.04.2015
Plant Load Factor       -     85%     

 

Southern Dagon Utility

Southern Dagon Utility (SDU) is the First Authorized Private Energy Company to distribute electricity in Myanmar for South Dagon Township, Yangon Region.

Type Of Project                                 -    Power Distribution to Consumers

Total Consumers                                -    Over 60,000 end users
 
Location                                            -    South Dagon Township, Yangon

Owner                                               -    Zeya and Associates Co., Ltd.

Date of Signing MOU                         -   01 April 2013
 

 

 

 

 

 

 

PROJECT EXPERIENCES OF POWER SYSTEMS

 

OUR EXPERIENCES

                                                                                                                                             
OUR EXPERIENCES

               
 

 

 

 

 

Project Title: The Supply of 132 kV Substation - 2 Lots, 66 kV Substations – 4 Lots, 66 kV Substation Extensions – 4 Lots,
                     66 kV Transmission Lines – 2 Lots, 33 kV Substation – 1 Lot
Location:      (1) Shwetaung  (2) Mone H.P.P  (3) Tat Kone  (4) Tanuaung   (5) Taungdwingyi
Owner:         Myanma Electric Power Enterprise and Directorate of Defense Industries
Start Date:   15 August 2006
Project Amount: 16,300,000.00 USD
Date of Completion: August 2008

 

 

OUR EXPERIENCES

Contract No:   F 58 (AS) 2008-2009
Project Title:  The Supply 132/66/11 kV, 60MVA Substation Materials
                       Project Buddhakone
Location:        Buddhakone
Owner:           Water Resources Utilization Department
Start Date:      23 March 2009
Project Amount: 2,950,000.00 USD
Completed Date: August 2010

 

 

OUR EXPERIENCES

Contract between International Contact and Zeya & Associates for 230/33/11 kV, 100 MVA Substation Materials
Project Title:      The Supply 230/33/11 kV, 100MVA Wartayar Substation Materials
Location:            Wartayar Industrial Zone
Owner:               DHSHD, Ministry of Construction
Start Date:          June 15, 2011
Project Amount: CIF 3,705,600.00 USD
Date of Completion: October 2012

 

 

OUR EXPERIENCES

Contract No:            105/EL-MEPE(PTP)/2010-2011|
Project Title:           Supply 230/66/11 kV,  100 MVA  Ahlone Substation Materials
Location:                 Yangon
Owner:                    Myanma Electric Power Enterprise
Start Date:               May 24, 2010
Project Amount:      1,800,000.00 Euro CIF
Date of Completion: February 2013